30 October 2015 
Rostov NPP: tests of polar crane done before installation of the reactor vessel at power unit №4 site

Tests of the polar crane with loads up to 462.5 tons were done with the help of special equipment in the reactor compartment of the power unit under construction №4 of the Rostov nuclear power plant.

22 October 2015 
Rostov NPP: there is a preparation for installation of the reactor vessel at power unit №4

One of the most significant events of the nearest prospects of the construction site is installation of the reactor pressure vessel taking place at the power unit №4

13 October 2015 
Rostov nuclear power plant passed comprehensive inspection of the State Corporation "Rosatom"

Inspection commission, chaired by Head of the Department for quality inspection, the General Inspectorate of the State Corporation "Rosatom" Stanislav Testova, within five days will be carrying out an audit of the technical, technological, fire and environmental safety

6 October 2015 
The Rostov NPP: installing of new modules for turbine condenser started at power unit №1

The first two modules of the turbine condenser, each weighing more than 80 tons, were given in the area of installation of the power unit №1 of the Rostov nuclear power plant on October 6, 2015.

29 September 2015 
Rostov nuclear power plant holds planned tactical exercises for brigade of internal troops

From September 28 to October 3, 2015 brigade tactical exercises are being held in the area of the Rostov NPP. The organizer of the exercises is the North Caucasian regional command of internal troops (IT) of the Rostov NPP.

24 September 2015 
Rostov NPP: unique operation on replacement of 1600-ton turbine condenser started at power unit №1

A unique operation on replacement of a turbine condenser modules with a total weight of 1,600 tons started on September 24, 2015 at the Rostov NPP.

23 September 2015 
Rostov nuclear power plant held planned command-staff exercises

Planned command-staff exercises (PCE) took place on September 23, 2015 on the territory of the Rostov NPP waterworks constructions.

18 September 2015 
Rostov NPP: power №3 accepted into commercial operation

Director of Capital Investments SC "Rosatom" Gennady Sakharov signed permission for commissioning of power unit № 3 of the Rostov NPP on September 17, 2015.

16 September 2015 
Rostov NPP: power unit №1 displayed into scheduled overhaul

The power unit №1 of the Rostov NPP was stopped for scheduled preventive average repair (PAR) on September 15, 2015 at 23:42. Beyond the PAR it is planned to do average repair of the reactor plant with refueling and performing of routine repairs of the main equipment.

16 September 2015 
The Rostov NPP: power unit №3 included into network after repair works

The power unit №3 of the Rostov NPP, which is in pilot operation, was included into the network after repair works on September 15, 2015, at 18:38.