Cannot find 'mainInNews' template with page '' RSS
Filter
Activity Start Date: Select date in calendarSelect date in calendar
  

14 July 2020  THE INFORMATION AND PUBLIC RELATION DEPARTMENT OF NOVOVORONEZH NPP
Rostekhnadzor has approved pilot production of the Novovoronezh NPP 6th power block in an 18-months’ fuel cycle
Rostekhnadzor has approved pilot production of the Novovoronezh NPP 6th power block in an 18-months’ fuel cycle
Rostekhnadzor (the Federal Service for Ecological, Technological and Nuclear Supervision) has issued a license to the Novovoronezh NPP for the pilot production of the Novovoronezh NPP 6th power block with a VVER-1200 reactor in the extended fuel cycle mode of 18 months.

8 July 2020  The Kursk NPP Information and Public Relations Department
The installation of the Russian tallest cooling tower pedestal columns has begun at the Kursk NPP-2
The installation of the Russian tallest cooling tower pedestal columns has begun at the Kursk NPP-2
The construction team has erected the first four columns of the 1st power block’s cooling tower base. All in all, 100 reinforced concrete columns will be installed circumferentially around the tower’s base. They will bear the load from the stack’s concrete covering.

3 July 2020  The Kursk NPP Information and Public Relations Department
The installation of the 2nd power block’s turbine set substructure skeleton pillars has been completed at the Kursk NPP-2
The installation of the 2nd power block’s turbine set substructure skeleton pillars has been completed at the Kursk NPP-2
The construction team has delivered another key milestone at the Kursk NPP-2 by completing the installation of twenty turbine set skeleton pillars from -7.000 to 0.000 mark at the 2nd power block’s turbine hall. It took 5 months for the team of AO ‘Titan-2 Company’ to complete the job.

1 July 2020  Press Service of AKKUYU NUCLEAR JSC
Second Tier of Internal Containment Installed at Power Unit 1 of Akkuyu NPP (Turkey)
Second Tier of Internal Containment Installed at Power Unit 1 of Akkuyu NPP (Turkey)
July 1, 2020, Büyükeceli, Mersin Province, Turkey. - The installation of the second tier of the reactor building's internal containment has been completed at the Power Unit 1 of Akkuyu NPP. Internal containment is one of the critical components of power unit's safety systems, which prevent release of radioactive materials to the environment.

30 June 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
HEAT FROM A FLOATING NUCLEAR POWER PLANT WAS FIRST DELIVERED TO THE CITY HEATING NETWORK IN PEVEK
HEAT FROM A FLOATING NUCLEAR POWER PLANT WAS FIRST DELIVERED TO THE CITY HEATING NETWORK IN PEVEK
June 30, 2020 – Today the first heat from the floating nuclear power plant (FNPP, the plant of JSC "Concern Rosenergoatom", Rosatom state atomic energy corporation’s division) was supplied to the 5th microdistrict of Pevek (Chukotka).

30 June 2020  Communications Department of ROSATOM
The full package of documents for obtaining a license for the construction of Paks-2 NPP has been submitted to the Hungarian Atomic Energy Authority
The full package of documents for obtaining a license for the construction of Paks-2 NPP has been submitted to the Hungarian Atomic Energy Authority
In line with the schedule, on 30 June 2020 the customer of the Paks II Nuclear Power Plant, Paks II. Ltd. submitted the implementation license application for the two new VVER-1200 3+ generation nuclear power plant units in Paks to the Hungarian Atomic Energy Authority (HAEA).

26 June 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
FOUR NEW NPP UNITS WILL BE BUILT IN RUSSIA
FOUR NEW NPP UNITS WILL BE BUILT IN RUSSIA
Preparations are now underway in Russia to build new power units in the Leningrad and Smolensk Regions. The corresponding decision was signed by Alexey Likhachev, Rosatom State Atomic Corporation Director General.

25 June 2020  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
The Leningrad NPP: the French team from MAN is leaving the construction site of the VVER-1200 2nd power block. The services at the backup diesel generating sets have been fully completed
The Leningrad NPP: the French team from MAN is leaving the construction site of the VVER-1200 2nd power block. The services at the backup diesel generating sets have been fully completed
On June 25, 2020, the VVER-1200 2nd power block of the Leningrad NPP held a ceremony of completing the services on the check-out of the critical equipment – the high-capacity diesel generating sets. The works were delivered by a combined team of the Leningrad NPP specialists and the companies that have manufactured this equipment - MAN Energy Solutions France SAS and Moteurs Leroy Somer (France).

17 June 2020 
 New business areas
New business areas
ROSATOM actively develops new business areas and enters new markets along with development of traditional businesses. According to ROSATOM’s strategy, proceeds from new businesses must be 30% of total proceeds by 2030.

17 June 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
The Kalininsky Data Centre of the Rosenergoatom Joint-Stock Company has presented its own cloud storage to host the data of the e-learning platform Allis.School
The Kalininsky Data Centre of the Rosenergoatom Joint-Stock Company has presented its own cloud storage to host the data of the e-learning platform Allis.School
The e-learning platform Allis.School, which has been developed as a part of the ‘Digital school’ federal project, is one of the key components in a digital learning environment.


Pages: 1 2 3 4 5 ... 321 Next