19 October 2015 
Bilibino NPP: power unit №3 shut down for scheduled overhaul

The third power unit of the Bilibino NPP was disconnected from the network and shut down for refueling and conducting preventative overhaul on October 16:00 hours 58 minutes local time. The planned average repair with duration of 60 days will last until December 14.

12 October 2015 
Bilibino NPP: repair of power unit №1 finished

A turbine generator of the power unit №1 of the Bilibino NPP was restarted after planned medium repairs on October 11, 13 hours 21 minutes local time.

2 October 2015 
The Bilibino NPP fulfilled September plan for electric power by 104,8%

The power units of the Bilibino developed 18,029 million KWh of electricity with a planned value of 17,029 million KWh in September 2015. Production plan was executed on 104,8%.

1 September 2015 
The Bilibino NPP exceeded August plan for electric power generation by 13%

The Bilibino NPP fulfilled plan for electricity production at 113.5%, it generated 18,898 million kWh with the planned target of 16,649 million kWh in August 2015.

14 August 2015 
The Bilibino NPP: power unit №1 displayed into scheduled overhaul

The Bilibino power unit №1 was disconnected from the network and shut down for refueling and conducting preventative overhaul on August 14, 2015, at 00:39 (local. Time). The planned average repair of 60 days will last until October 12.

10 August 2015 
The Bilibino NPP: repair of power unit №2 completed three days ahead of schedule

Planned average repair of the power unit № 2 was ended at the Bilibino NPP ahead of schedule on three days. It was plugged in August 7, 2015, at 20:45.

5 August 2015 
The Bilibino NPP generated over 15.9 million KWh in July

The Bilibino NPP produced 15.970 million KWh of electricity with the plan of 15,901 million KWh in July 2015.

21 July 2015 
The Bilibino NPP: All-Russian charity event "Day of Knowledge in New Russia" finished

Fund-raising was organized at the Bilibino NPP beyond the All-Russian charity event "Day of Knowledge in New Russia"

3 July 2015 
The Bilibino NPP: scheduled overhaul of old equipment and pipelines main heating systems started

The Bilibino NPP holds summer planned overhaul of equipment and pipelines of the main heating systems from July 1 to July 14, 2015.

2 July 2015 
The Bilibino NPP: plan for electric power made at 106.5% in June

The Bilibino NPP generated 16.831 million KWh of electricity in June 2015  instead of planned value of 15.866 KWh, consumers were released 13,178 million KWh (plan - 12,366 million KWh), supply of heat from the collectors was 3,213 thousand Gcal