06.02.2014 17:23 

The Novovoronezhskaya nuclear power plant: the plan of January for development of the electric power implemented for 104,96 percent

In January, 2014 the Novovoronezhskaya nuclear power plant developed 1407,5 million kWh of the electric power. The plan for the electric power development, approved by Federal Tariff Service, was executed for 104,96% in January. In the power supply system 1314,7 million kWh of the electric power, that constitutes 105,26% of the plan, were released.

The installed capacity utilization rate on the Novovoronezhskaya nuclear power plant in January made – 103,15% (planned KIUM – 98,28%).

There are power units No. 3, No. 4 and No. 5 of the Novovoronezhskaya nuclear power plant in work in the set mode at the moment.

The radiation background at the station and the adjacent territory is at the level corresponding to normal operation of the power units, and doesn't exceed natural background values, characteristic for the Central European part of Russia.

Current information about a radiation situation near the nuclear power plant in Russia and other objects of the nuclear industry is provided on a site www.russianatom.ru.

The Novovoronezhskaya nuclear power plant is a branch of JSC "Concern Rosenergoatom". The station is located on the bank of the Don River in 42 km to the south of Voronezh. It is the Russia's first nuclear power plant with VVER reactors (water-to-water power reactors of case type with regular water under pressure). Each of five reactors of station is head – a prototype of serial power reactors: the power unit No. 1 with the VVER-210 reactor, the power unit No. 2 with the VVER-365 reactor, No. No. 3, 4 power units with VVER-440 reactors, the power unit No. 5 with the VVER-1000 reactor. The first power unit was launched in 1964, the second – in the 1969, third – in the 1971, fourth – the 1972, fifth – 1979.

There are three power units (power units (No No 1, 2 we're stopped in 1984 and 1990 years respectively) on work at the moment.