The Balakovo nuclear power plant: the plan forJanuary was implemented for 106,5 percent
The Balakovo nuclear power plant executed he Plan target for January, 2014 for 106,5 percent.
Last month the station developed 2 373 732,828 thousand kWh of the electric power in case of the plan of 2 228 million kW of h of the electric power.
The Installed Capacity Utilization Rate (ICUR) made 79,76%.
The Balakovo nuclear power plant in January worked safely and reliably.
There are power unit No. No. 1, 3, 4 in work at the moment. The power unit No. 2 is in planned repair.