04.02.2014 18:05 

The Balakovo nuclear power plant: the plan forJanuary was implemented for 106,5 percent

The Balakovo nuclear power plant executed he Plan target for January, 2014 for 106,5 percent.

Last month the station developed 2 373 732,828 thousand kWh of the electric power in case of the plan of 2 228 million kW of h of the electric power.

The Installed Capacity Utilization Rate (ICUR) made 79,76%.

The Balakovo nuclear power plant in January worked safely and reliably.

There are power unit No. No. 1, 3, 4 in work at the moment. The power unit No. 2 is in planned repair.

Current information about the work of the station is available on the clock telephone-answering machine of the Balakovo NPP social information center (845-3) 62-22-20.

Current information about a radiation situation near the nuclear power plant in Russia and other objects of the nuclear industry is provided on a site www.russianatom.ru.


Back to the list