04.12.2014 09:41 

The Balakovo NPP: plan executed on 108.4 percent in November

The Balakovo NPP fulfilled the planned target for November 2014 on 108.4 percent. The station generated 2599,45 million kWh of electricity at the plan of 2.399 billion kWh last month.

The capacity factor (load factor) was 90.26%.

The Balakovo NPP worked safely and efficiently in November.

There are power units №1 and №4 in work at the moment. Power units №2 and №3 are being repaired.

Updated information about the nuclear power plant can be found on the phone answering machine in the Public Information Centre of the Balakovo NPP (845-3) 62-22-20.