08.07.2014 09:09 

The Balakovo NPP: 2014 June plan made 104.8 percent

The Balakovo NPP performed June 2014 planned job at 104.8 percent. Last month, the station generated 2,245,800, 816 thousand kWh of electricity in terms of 2142 million kilowatt hours of electricity.

The capacity factor (load factor) was 77.98%.

On June 28 at 6 hours 30 minutes (MSK) the Balakovo NPP power unit №1 was plugged in after the planned average repair with refueling. Repairs were completed ahead of the schedule and with proper quality. Shortening of the repair work was 9.8 days.

There are all four power units in work at the Balakovo NPP.

Current information about the work of the station is available on the clock telephone-answering machine of the Balakovo NPP social information center (845-3) 62-22-20.

Current information about a radiation situation near the nuclear power plant in Russia and other objects of the nuclear industry is provided on a site www.russianatom.ru.