The Kalininskaya NPP: March plan has been fulfilled on 106.8%

The Kalininskaya NPP in March 2014 fulfilled targets for production and supply of electricity.

So, in March the Kalininskaya NPP developed 2,348 billion kWh (106.8%). In grid released 2,225 billion kWh (107.4%). The capacity factor (load factor) in March was 78.90% (73.89% at the plan).
In total from the beginning of the year the Kalininskaya NPP generated 6,984 billion kWh (105.5%), in the grid was released 6.626 billion kWh (106.2%).

There are three power units of the Kalininskaya nuclear power plant in work at the moment. The power unit №1 is in planned overhaul.

The radiation background on the nuclear power plant and around its arrangement is at the level corresponding to normal operation of power units, and doesn't exceed natural background values.

The Kalininskaya nuclear power plant is a branch of JSC "Concern Rosenergoatom". The station is located in the north of the Tver region in the Udomelskiy area. There are four power units with water-cooled power reactors (VVER-1000) with installed capacity of 1000 MW each in the structure of the Kalininskaya nuclear power station.