24 October 2023  THE SMOLENSK NPP INFORMATION AND PUBLIC RELATIONS DEPARTMENT
The international insurance inspection confirmed the high level of safety of the Smolensk NPP
23 October 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
At power unit No. 1 of the Kursk NPP-2, one of the most important pre-start-up technological operations is pouring the safety systems onto an open reactor
At power unit No. 1 of the Kursk NPP-2, one of the most important pre-start-up technological operations is pouring the safety systems onto an open reactor
On October 19, 2023, at power unit No. 1 of the replacement station, the leakage of safety systems into the open PWR-TOI reactor began
16 October 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
At the Kursk NPP-2, work on concreting the dome of the internal containment of the second power unit has been completed
At the Kursk NPP-2, work on concreting the dome of the internal containment of the second power unit has been completed
In the reactor building of the second power unit, concreting of the dome of the internal containment has been complete
9 October 2023  Department of Information and Public Relations of the Kalinin NPP
A delegation from the Akkuyu NPP visited the Kalinin Nuclear Power Plant to study the experience of selling electricity
A delegation from the Akkuyu NPP visited the Kalinin Nuclear Power Plant to study the experience of selling electricity
The delegation of AKKUYU NUCLEAR JSC visited the Kalinin Nuclear Power Plant as part of a seminar organized by Rosenergoatom together with the World Association of Nuclear Power Plant Operators to study advanced experience in selling electricity
22 September 2023  THE SMOLENSK NPP INFORMATION AND PUBLIC RELATIONS DEPARTMENT
WANO experts highly appreciated the level of operation of the Smolensk nuclear power plant
WANO experts highly appreciated the level of operation of the Smolensk nuclear power plant
At the Smolensk NPP, the first in Rosenergoatom, a new format of interaction with the World Association of Nuclear Power Plant Operators was tested
13 September 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
At the construction site of the Leningrad NPP, a foundation pit is ready for the construction of the reactor building of the new PWR-1200 power unit No. 7
At the construction site of the Leningrad NPP, a foundation pit is ready for the construction of the reactor building of the new PWR-1200 power unit No. 7
At the construction site of the Leningrad NPP, the main excavation work has been completed to develop a pit for the nuclear island of power unit No. 7 of PWR-1200
4 September 2023  COMMUNIKATIONS DEPARTAMENT OF ROSENERGOATOM
The work of Russian nuclear power plants for eight months made it possible to prevent emissions of about 70 million tons of greenhouse gases into the atmosphere
The work of Russian nuclear power plants for eight months made it possible to prevent emissions of about 70 million tons of greenhouse gases into the atmosphere
Russian nuclear power plants (branches of Rosenergoatom, Electric Power Division of Rosatom State Corporation) generated over 141.8 billion kilowatt-hours or 102.03% of the balance task of the Federal Antimonopoly Service (FAS) of Russia in eight months of 2023
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
Concreting of the dome of the outer containment of power unit No. 1 was completed at the construction site of the Kursk NPP-2
Concreting of the dome of the outer containment of power unit No. 1 was completed at the construction site of the Kursk NPP-2
The outer containment (OC) is one of the physical barriers that protect the reactor plant from extreme external influences, which is a reinforced concrete structure
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF BELOYARSK NPP
Steam generators of power unit No. 3 of the Beloyarsk NPP are being modernized to extend the service life until 2040
Steam generators of power unit No. 3 of the Beloyarsk NPP are being modernized to extend the service life until 2040
On August 24, power unit No. 3 with a BN-600 fast neutron reactor at the Beloyarsk NPP was taken out of service for scheduled preventive repair in order to carry out fuel refueling, and preventive maintenance of the main equipment. The main work will be the replacement of eight evaporative modules of steam generators
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF ROSTOV NPP
The Rostov NPP: modernization of the cooling system made it possible not to reduce the capacity of power unit No. 3 during the summer maximum temperatures
The Rostov NPP: modernization of the cooling system made it possible not to reduce the capacity of power unit No. 3 during the summer maximum temperatures
Since the beginning of summer, power unit No. 3 of the Rostov NPP, operating with the support of fan cooling towers, has not been allowed to reduce power due to high air temperatures. The unit operates without restrictions, providing planned electricity generation for consumers in the South of Russia