09.08.2013 

On the Baltic nuclear power plant works on installation of a protective cover of a reactor building of the first power unit are being continued

On a building site of the Baltic nuclear power plant is almost completed the device of ferro-concrete constructions of internal structures of the reactor building of the power unit No. 1 Works from a mark-3,850 to a mark-1,250 are performed by builders of contract organization JSC "OEK" "The joint power construction corporation", Moscow) under control of Rosenergoatom Concern branch of JSC "Management of the Baltic nuclear power plant under construction" and the prime contractor of JSC "NIAEP".

In the mine of the reactor of the first power unit where "trap" has been  established (ULR i- the device of localization of fusion), intended for a deduction of the melted nuclear fuel, works on drawing anticorrosive protection of metal facing are conducted. The covering of 200 microns thick is put with a method of arc metallization.

According to the approved thematic plan works on other objects of the power unit No. 1 are proceeded. So, in the safety building specialists of contract organization "Stroytekhsistem" are carrying out works on overlapping concreting on a mark of-3,700 m. On the object "The management building" builders of JSC "SMU-1" are putting up walls from a mark of-3,700 m to a mark 0,400M



Back to the list