06.04.2012  Public Information Centre of Novovoronezh NPP

Novovoronezh NPP has implemented a plan for March for 104.09 percent

In March, 2012 the power units of Novovoronezh NPP have generated 1389.6 mln kWh of electric power. The electric power generation plan, approved by the Federal Tariff Service of Russia, is implemented for 104.09 %.

In March the power system has received 1302.9 mln kWh of electric power, that amounts to 104.74 % of the plan.
The unit capability factor (UCF) has made 101.84 % (at the UCF plan of    97.84 %).

In total since the beginning of 2012, there has been generated 4014.0 mln kWh of electric power, or 102.4 % of the planned target of FTS. The power system has received 3760.4 mln kWh, or 102.91 % of the plan. The unit capability factor for two months has made 100.21 % (it is 97.87 % of the plan).

At present, Novovoronezh NPP operates the power units No.3, 4 and 5. The power units operate at the capacity specified by the dispatch schedule.
In March, 2012, there were no any violations of conditions and normal operation limits of the plant power units.

 The radiation background on the area of the plant and the adjacent territory corresponds to the level of power unitsХ normal operation and does not exceed the natural environmental values.

On line detailed data on the radiation environment near nuclear power plants in Russia and other nuclear facilities is provided on site russianatom.ru