21.08.2013 

Leningrad NPP-2: on a building site took place next meeting of operational staff

On August 6, 2013 on a building site of the Leningrad NPP-2 took place the next meeting of operational staff on a construction of the 1st and 2nd power units under the chairmanship of the deputy director general of JSC ЗRosenergoatom ConcernИ - directors of the branch of JSC ЗRosenergoatom ConcernИ ЗManagement of a construction of objectsИ Alexander Palamarchuk.

In 7 months 2013 on the building of the reactor of the power unit No. 1 internal protective cover (IPC) concreting is executed at mark +31,50; external protective cover (EPC) concreting to mark +39,50; concreting of internal construction designs to mark +14,50; concreting of mine of the reactor and mines of audit of the block of protective pipes and intra case devices from mark +8,00 to mark +11,27; installation of the lower plate of the device of localization of fusion, was established the basic farm of the reactor, welding works on installation of the console of subcrane beams of the power unit No. 1 are performed for 100%.

On the building of the turbine of the power unit No. 1 four heaters of a high pressure are established on a regular place; the last stage of installation of four separators of boiler superheaters has been begun.

On the building of the reactor of the power unit No. 2 works on the device of facing of VZO to mark + 9,40 are performed, preparation for the beginning of concreting of VZO to mark +9,40 comes to the end, concreting of NZO is executed to mark +9,25 . ULR case installation is also executed.

On the building of the turbine of the power unit No. 2 concreting of walls to mark  +36,70s completed.

The number of the qualified construction personnel occupied on a construction of objects of the Leningrad NPP-2, averages 2 899 people. For the purpose of further building-up of number of highly skilled workers on a building site are developed measures by the heads of the General contractor.

The special attention is paid to questions of equipment supply and its quality, creation of dispatching service for the operational solution of questions power - water - and heat supplies of the construction platform.

At the meeting of the staff were heard results of checks on labor protection, the fire and industrial safety, carried out by inspection services on the building site of the Leningrad NPP-2 in July. Work on increase of safety personal culture of the construction personnel are proceeded.

In the report the director of the JSC ЗConcern RosenergoatomИ branch  ЗManagement of the Leningrad NPP-2И Yury Galanchuk analysed accomplishment of an investing program and programs about construction and design and exploration work, set tasks to the general contractor and the generating designer for August, among which: to continue building-up of the number of the personnel on a building site of the Leningrad NPP-2, to increase the regular number of geodesy service, to create scheduling service of the Leningrad NPP-2 construction, to provide accomplishment of planned indicators on design and exploration work and equipment supply, control events accomplishment ofn August.

Summing up the meeting, the deputy director general of the JSC ЗRosenergoatom ConcernИ Alexander Palamarchuk noted that it is necessary to develop compensating measures on a set of the assembly personnel, to enhance engineering procedures, to organize enlarging assembly of the building roof of the power unit No. 2 turbine, to a management of JSC SPBAEP to create group of design engineering directly on a building site.

ЗWe have necessary resources, they are sufficient to carry out all key tasks and an investing program of the yearИ, - told during the summing up A.Palamarchuk.