Beloyarsk NPP has fulfilled in advance the annual plan by generating over 7.8 billion KWh of electric energy

Beloyarsk NPP reached the target level of the annual plan of electric energy generation by producing 7.83 billion kWh. Rosenergoatom Concern has identified this level as target for the Beloyarsk NPP within the 2016 team key performance indicator for the volume of electric energy production.

The power unit No 3 (BN-600) in particular has produced 4.37 billion kWh of electric energy, and the power unit No 4 (BN-800) has produced 3.46 billion kWh of electric energy.

At the present moment Beloyarsk NPP generates the electric energy above the planned target level Р a new electric year at the plant has started.

The Beloyarsk NPP has come into operation in April 1964. The first power blocks of the Beloyarsk NPP with thermal reactors AMB-100 and AMB-200 has been closed after the accumulated running time. The power block with a fast industrial capacity reactor BN-600 is still on. The power block with a fact reactor BN-800? is currently being prepared for coming into operation.