23.10.2015 

All-Russian Research Institute of Nuclear Power Operations began installing a new ASC TP at new power unit of RoNPP

Experts of the ARRINPO started installation of automatic control system of technological process on the power unit ?4 being built at the Rostov NPP. Engineers and technicians are installing and debugging the system of the upper block level as well as control systems and electrical low-voltage devices, which have been set by the "ARRINPO" at the platform of the power unit.

The equipment was delivered to the NPP site in late September. Completion of installation and debugging of the ACS, which is the "electronic brains" of the NPP, are planned to be done in 2017.

Another system for control and management of electrical equipment arrived in July. It is necessary to provide the supply of voltage for auxiliaries units under construction, which is planned for the end of December 2015.

These systems are similar to the equipment used at the power unit ?3 of the Rostov NPP.