The Beloyarsk NPP: maintenance is on schedule

Planned refueling of the reactor BN-600 unit of the Beloyarsk NPP completed. Maintenance of the power unit equipment. In particular, the next major overhaul of the generator №5 and average repair of the low pressure turbine cylinder №6, as well as maintenance work on other equipment have been carried out.

6 April 2015 
The Beloyarsk NPP: planned activities will be carried out from April 7 at the power unit №3

On April 7, 2015 the power unit №3 with the reactor BN-600 of the Beloyarsk NPP suspends work in connection with the planned measures: refueling, maintenance and repair of equipment. In particular, it is necessary to perform overhaul repair of one of the turbogenerators.

6 April 2015 
The Beloyarsk NPP: it was produced over 457,46 million KWh of electricity in March

In March 2015 the power unit №3 with the BN-600 reactor at the Beloyarsk NPP generated more than 457,46 million kilowatt-hours of electricity.

3 March 2015 
The Beloyarsk NPP produced over 399,5 million KWh of electricity in February

The power unit №3 with the BN-600 reactor of the Beloyarsk NPP generated more than 399.5 million Kilowatt-hours of electricity in February 2015,.

1 March 2015 
The Beloyarsk NPP: BN-600 reactor injected into the nominal power level

The power unit №3 with the reactor BN-600 was launched into the nominal power level on the night of February 25.

6 February 2015 
The Beloyarsk NPP: BN-600 developed more than 456,9 million KWh of electricity in January

The power unit №3 with the BN-600 reactor at the Beloyarsk NPP generated more than 456.9 million Kilowatt-hours of electricity in January 2015,.

16 January 2015 
Power unit №3 of the Balakovo NPP restarted

The power unit №3 of the Balakovo NPP (Saratov region) was plugged in after graduating from preventative maintenance on the basis of the obtained permission of the «Rosenergoatom Concern» on January 15, 2015 at 9 o'clock 07 minutes. The power unit was under repair from 23 November 2014.

26 December 2014 
The Beloyarsk NPP summed up the year

Golden Anniversary year was full of important events for the Beloyarsk NPP.

11 December 2014 
Valuable data for improvement of fuel provided due to the success of the BN-800 reactor at the stage of physical start-up

"Even at the stage of physical start-up of the BN-800 reactor, held this year, valuable data for the development of nuclear fuel was provided. The improvement has already been running "

28 November 2014 
The Beloyarsk NPP: Zarechny doctors training the activities of nuclear power plantson webinar

Doctors from urban district Zarechnyi (Sverdlovsk region) were training on the two-day seminar via videoconference (webinar), which was organized by the JSC "Concern Rosenergoatom" and non-governmental Ecological Fund of V.I. Vernadsky.


Pages: Prev. 1 2 3 4 5 ... 10 Next