Kalinin NPP

Kalinin NPP
4 000 MW

total installed capacity

At NPP site it was constructed “Kalininskiy” Data Storage and Processing Center – the first one in Rosenergoatom’s data centers network

Unit in operation

  • 01 block

    VVER-1000

    1000 MW

  • 02 block

    VVER-1000

    1000 MW

  • 03 block

    VVER-1000

    1000 MW

  • 04 block

    VVER-1000

    1000 MW

Power start date

Reactor Type

Installed capacity

Statistics

Tver region

Tver region

Kalinin NPP

Udomlya

  • 4 KM

    to Udomlya host town

  • 125 KM

    to Tver regional city

  • 663,67 billion kWh

    electricity since Unit 1 start up Kalinin NPP

  • 28 492,1 million KWh

    electricity generation in 2020

  • 14,3 th. tons

    СО₂ equivalent emissions savings equal in 2020

  • 360,461 million rubles

    environment protection costs amount

Performance Indicators:

  • 91,8%
    electricity generation vs. 2019
  • 102,5%
    performance of RF FAS balance
  • 81,1%
    capacity factor
  • 13,2%
    of all electricity generated in Rosenergoatom