5 February 2024  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
The first meeting of the headquarters this year was held at the construction site of Kursk NPP-2
The first meeting of the headquarters this year was held at the construction site of Kursk NPP-2
The managers noted the high pace and quality of construction of new innovative PWR-TOI power units

1 February 2024  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
Power unit No. 2 of the Kursk NPP was taken out of power generation mode after 45 years of successful operation
Power unit No. 2 of the Kursk NPP was taken out of power generation mode after 45 years of successful operation
Its power will be replaced by the PWR-TOI power unit under construction
29 January 2024 
At the construction site of power unit No. 2 of the Kursk NPP-2, work began on welding the main circulation pipeline
At the construction site of power unit No. 2 of the Kursk NPP-2, work began on welding the main circulation pipeline
The walls of the MCP are made of steel 7 cm thick, the total mass of pipelines and metal structures will exceed 250 tons
22 January 2024  COMMUNIKATIONS DEPARTAMENT OF ROSENERGOATOM
In 2023, about 700 foreign nuclear workers were trained and improved their skills at Russian nuclear power plants
In 2023, about 700 foreign nuclear workers were trained and improved their skills at Russian nuclear power plants
In Russia, all the necessary conditions have been created that meet international standards in the sphere of personnel training for nuclear power plants, including foreign ones
18 December 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
A delegation of representatives of the Turkish Nuclear Regulatory Agency visited the Novovoronezh NPP
A delegation of representatives of the Turkish Nuclear Regulatory Agency visited the Novovoronezh NPP
During the visit, the training process of the Akkuyu NPP specialists was monitored
6 December 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
At power unit No. 2 of Kursk NPP-2, which is under construction, all four steam generators were installed in the design position
1 December 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
At the construction site of Kursk NPP-2, the reactor vessel of power unit No. 2 was installed in the design position
At the construction site of Kursk NPP-2, the reactor vessel of power unit No. 2 was installed in the design position
This is one of the most important operations from which the countdown begins before commissioning begins
27 November 2023  THE INFORMATION AND PUBLIC RELATION DEPARTMENT OF NOVOVORONEZH NPP
Novovoronezh nuclear scientists were the first to work on converting a power unit from PWR-1200 to an 18-month fuel cycle
Novovoronezh nuclear scientists were the first to work on converting a power unit from PWR-1200 to an 18-month fuel cycle
After receiving an expert opinion and changing the terms of the license, unit No. 6 will be transferred to industrial operation in a new mode
27 November 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF BELOYARSK NPP
The world's first IAEA OSART mission on a power unit with a fast neutron reactor was completed at the Beloyarsk NPP
The world's first IAEA OSART mission on a power unit with a fast neutron reactor was completed at the Beloyarsk NPP
International IAEA experts highly appreciated the safety level of the Beloyarsk NPP
23 November 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
At the Kursk NPP the last fuel assembly was unloaded from the reactor of power unit No. 1
At the Kursk NPP the last fuel assembly was unloaded from the reactor of power unit No. 1
The first stage of preparation for decommissioning of the unit was completed ahead of schedule