RSS
Filter
Activity Start Date: Select date in calendarSelect date in calendar
  

5 August 2020  THE KURSK NPP INFORMATION AND PUBLIC RELATIONS DEPARTMENT
The assembly of the inner containment’s third floor has been completed at the Kursk NPP-2 1st power unit
The assembly of the inner containment’s third floor has been completed at the Kursk NPP-2 1st power unit
The team has installed the final, eleventh, reinforcement block for the reactor containment’s third floor at the Kursk NPP-2 1st power unit under construction. Thus, the construction team has completed the assembly of the containment’s cylindrical piece. This will be followed by three floors of the crestal area.

4 August 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
Rosenergoatom has resumed the HR labs on the implementation of Industry 4.0.* technologies
Rosenergoatom has resumed the HR labs on the implementation of Industry 4.0.* technologies
HR Tech Lab 2.0., the first lab to take place in 2020, was dedicated to HR robot process automation as a part of the staff digital transformation. The lab was attended by representatives of the Rosenergoatom Joint-Stock Company’s HQ, the NPPs’ and the affiliate companies’ HR departments.

22 July 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
Rosenergoatom is setting up the RBMK units final shutdown engineering center in St Petersburg
Rosenergoatom is setting up the RBMK units final shutdown engineering center in St Petersburg
Under the auspices of the Leningrad NPP (city of Sosnovy Bor, the Leningrad region), a new pilot and demonstration engineering center in charge of NPP channel-type reactor facility power units (RBMK) final shutdown has been established.

20 July 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
ROSATOM: FUEL LOADING STARTS AT POWER UNIT 2 OF LENINGRAD NPP-2
Sosnovy Bor, July 19, 2020. The first of 163 nuclear fuel assemblies has been loaded into the VVER-1200 reactor of power unit 2 of Leningrad NPP-2. Fuel loading marks the beginning of the physical start-up of an NPP. The plant is operated by Rosatom’s Electric Power Division Rosenergoatom.

17 July 2020  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
The Leningrad NPP: Rostekhnadzor has issued an approval for the operation of the new 6th VVER-1200 power unit
The Leningrad NPP: Rostekhnadzor has issued an approval for the operation of the new 6th VVER-1200 power unit
The commission of the Federal Service for Ecological, Technological and Nuclear Supervision (Rostekhnadzor) has issued a license to operate the 6th VVER-1200 power unit of the Leningrad NPP.

14 July 2020  THE INFORMATION AND PUBLIC RELATION DEPARTMENT OF NOVOVORONEZH NPP
Rostekhnadzor has approved pilot production of the Novovoronezh NPP 6th power unit in an 18-months’ fuel cycle
Rostekhnadzor has approved pilot production of the Novovoronezh NPP 6th power unit in an 18-months’ fuel cycle
Rostekhnadzor (the Federal Service for Ecological, Technological and Nuclear Supervision) has issued a license to the Novovoronezh NPP for the pilot production of the Novovoronezh NPP 6th power unit with a VVER-1200 reactor in the extended fuel cycle mode of 18 months.

8 July 2020  The Kursk NPP Information and Public Relations Department
The installation of the Russian tallest cooling tower pedestal columns has begun at the Kursk NPP-2
The installation of the Russian tallest cooling tower pedestal columns has begun at the Kursk NPP-2
The construction team has erected the first four columns of the 1st power block’s cooling tower base. All in all, 100 reinforced concrete columns will be installed circumferentially around the tower’s base. They will bear the load from the stack’s concrete covering.

3 July 2020  The Kursk NPP Information and Public Relations Department
The installation of the 2nd power unit’s turbine set substructure skeleton pillars has been completed at the Kursk NPP-2
The installation of the 2nd power unit’s turbine set substructure skeleton pillars has been completed at the Kursk NPP-2
The construction team has delivered another key milestone at the Kursk NPP-2 by completing the installation of twenty turbine set skeleton pillars from -7.000 to 0.000 mark at the 2nd power unit’s turbine hall. It took 5 months for the team of AO ‘Titan-2 Company’ to complete the job.

30 June 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
HEAT FROM A FLOATING NUCLEAR POWER PLANT WAS FIRST DELIVERED TO THE CITY HEATING NETWORK IN PEVEK
HEAT FROM A FLOATING NUCLEAR POWER PLANT WAS FIRST DELIVERED TO THE CITY HEATING NETWORK IN PEVEK
June 30, 2020 – Today the first heat from the floating nuclear power plant (FNPP, the plant of JSC Rosenergoatom, Rosatom state atomic energy corporation’s division) was supplied to the 5th microdistrict of Pevek (Chukotka).

26 June 2020  COMMUNICATIONS DEPARTMENT OF ROSENERGOATOM
FOUR NEW NPP UNITS WILL BE BUILT IN RUSSIA
FOUR NEW NPP UNITS WILL BE BUILT IN RUSSIA
Preparations are now underway in Russia to build new power units in the Leningrad and Smolensk Regions. The corresponding decision was signed by Alexey Likhachev, Rosatom State Atomic Corporation Director General.


Pages: Prev. 1 2 3 4 5 ... 39 Next