04.02.2015 

The Novovoronezh NPP: electricity production plan in January 2015 made on 104.65%

The Novovoronezh nuclear power plant produced 1,402, million KWh of electric energy. Electricity production plan, approved by the Federal Tariff Service (FTS) of Russia, in the month of January was made on 104.65%. It was released 1311,6 million KWh of electricity into the grid, which is 105.10% of the plan.

The capacity factor at the Novovoronezh NPP in January was 102.77% (planned capacity factor - 98.20%).

The Novovoronezhskaya nuclear power plant is a branch of the JSC "Concern Rosenergoatom". The station is located on the bank of the Don River in 42 km to the south of Voronezh. It is the Russia's first nuclear power plant with VVER reactors (water-to-water power reactors of case type with regular water under pressure). Each of five reactors of the station can be a main one – a prototype of serial power reactors: the power unit No. 1 with the VVER-210 reactor, the power unit No. 2 with the VVER-365 reactor, the No. 3, 4 power units with the VVER-440 reactors, the power unit No. 5 with the VVER-1000 reactor. The first power unit was launched in 1964, the second – in 1969, third – in 1971, fourth – 1972, fifth – 1979.

There are three power units (power units No.1, 2 were stopped in 1984 and 1990 respectively) in work at the moment.

Construction of two innovative power blocks ?6 and ?7 with capacity of 1200 Wt has been done since 2007 at the site of Novovoronezh NPP.

Average values of radiation background correspond to level of natural background values in the Central European Part of Russia in settlements of a 30-km zone round the Novovoronezhskaya nuclear power plant.

Updated nformation about radiation situation near the nuclear power plants in Russia and other objects of the nuclear industry is provided on a site www.russianatom.ru.