26 April 2016  The Leningrad NPP Information and Public Relations Administration
The Leningrad NPP: the main circulation line’s welding at the power block No.1 under construction complies with the technical specification
The welded connections of the main circulation line at the Leningrad NPP power block No.1 being constructed are completed in a proper way and comply with the technical specification, which was confirmed during the issue-related verification carried out jointly by the representatives of the Leningrad NPP and VNIIAES.
25 April 2016  The Rostov NPP Information and Public Relations Administration
The Rostov NPP: the electric pumps for water supply to the main circulation pump air coolers have been installed at the machine hall of the power block No.4 under construction
The Volgodonsk installation department has completed the NKU-250 electric pumps installation at the machine hall of the power block No.4 under construction. The pumps are designed to transmit water into the main circulation pumps’ engine coolers.
25 April 2016  The Leningrad NPP Information and Public Relations Administration
The Leningrad NPP: a new 110/10 kW sub-station was launched to cater for the power block No.1 in-house needs
The Leningrad NPP has just completed one of the key events in any nuclear power station construction: the 110/10 kW sub-station equipment has been energized. The latter was announced during the daily briefing held by the Rosenergoatom Concern OJSC director Andrey Petrov.
25 April 2016  The Leningrad NPP Information and Public Relations Administration
The Leningrad NPP is a unique point for sharing best practices in nuclear power station security provision
On April 22, 2016, the representatives of the Board of governors for the World Association of Nuclear operators have paid a visit to both the operating and the undergoing construction power blocks of the Leningrad NPP to learn more about its service and the best practices in security.
25 April 2016 
Cooperation Agreement signed between Electricite de France and Rosenergoatom
Electricite de France (EDF) and Rosenergoatom Concern signed a cooperation agreement.
22 April 2016  Novovoronezh NPP Information and Public Relations Administration
The Novovoronezh NPP: the innovative power block No.6 is to achieve its minimum controllable power level in May 2016
The innovative Novovoronezh NPP power block No.6 might achieve its minimum controllable power level early May 2016, as the plant’s director Vladimir Povarov reported at the daily briefing on April 21.
22 April 2016  The VNIIAES media center
VNIIAES: the Rostov NPP power block No.3 simulator trial has been completed
On April 22, 2016, the Rostov NPP power block No.3 simulator (PMT-3) has undergone the acceptance trial.
20 April 2016  The Leningrad NPP Information and Public Relations Administration
The Leningrad NPP first power block’s reactor external containment has been concreted
One of the key milestones of the Leningrad NPP replacement capacities’ construction has been achieved, with the reactor external containment being fully concreted. During the last stage of works, the constructions laid around 118 cubic meters of concrete using spud vibrators to condense it and special trowels to even.
18 April 2016  The Rostov NPP Information and Public Relations Administration
The Rostov NPP: the turbine feed pumps and 70% of the pipes have been installed at the turbine hall of the power block No.4 under construction
70% of the pipes with the total weight of over 1.5 tons have been installed in the turbine hall of the power block No.4 currently under construction. The latter was reported by Alexander Goremykin, the contractor’s (the Volgodonsk installation department) director.
18 April 2016  The Leningrad NPP Information and Public Relations Administration
The Leningrad NPP: the primary coolant permanent purification filters have been installed at the power block No.1 under construction
The primary coolant permanent purification installation is still in progress at the Leningrad NPP power block No.1. The contracting organization has already installed two ion exchange filters to the proper locations, those being large-sized equipment: each filter weighs 9.5 tons, is over 5 meters high with the diameter of 1.2 meters.